Next Steps:

Jan '07
1. Finish painting inside of shop and office.
2. Complete inside work (flooring, lighting, etc.)
3. Move into office (desks, computers, bookshelves, etc.)
4. Move into shop (workbenches, tools, shelving, sink, fridge, etc.)

Feb '07
1. Begin to sort through all of the documentation from George
(Manuals, plans, drawings, etc.).
2. Research and build a wing jig.
3. Locate nearest supplier of sheet aluminum.
4. Collaborate w/ Cabi to layout and cut wing spars.
(He's got a plasma cutter - way cool tool!)

Mar '07
1. Repair and install hydraulic press in preparation
for punching out wing ribs.
2. Layout and cut wing ribs.
3. As the weather warms up, finish painting the
exterior of the shop.

What's Up So Far???

Here's what we've done so far:



1. Bought the company.

In the summer of 2005 several meetings were held and the newly formed partnership of ALPHAmax Aircraft, LLC purchased Prowler Aviation, Inc. ALPHAmax Aircraft has now assumed all the associated tangible and intellectual property. We are now in the process of organizing and inventorying all of the property from the sale.



2. Created a website.

Check it out!----> www.prowleraviation.com

3. Building a shop.


These are pictures of the "Prowler Aviaiton -West" shop in northern California. This is where we will build our first Prowler kit and then assemble the kit to produce our first aircraft. What we learn about the building processes as well as other information from this work will later be used to gear the kit for large(r) scale production.